Shady Dale roadwork continues through Oct. 27

On Oct. 21, Georgia Department of Transportation contractors began a $680,000 micro-seal surface treatment project to preserve State Route 142 from the State Route 16 intersection to the Jasper County line.

Expect delays in the 6-mile work zone from 8 a.m. to 5 p.m. when workers are present. The current plan allows Monday through Saturday work with this initial phase finishing Friday, Oct. 27. Contractors will return for more finishing activity in the coming weeks.

Chip seal and a final micro seal asphalt layer will complete the roadway preservation, fixing any cracking or other surface issues identified in the corridor.

Traffic will move about the area via a flagging operation.

Source: The Georgia Dept. of Transportation